New houses
Search
Further information
Recently viewed developments
  • Here we will display your last 5 viewed developments
Shortlist
There are no developments in your shortlist. You can add developments here by clicking the "add to shortlist" link within the development page

Building your new home

Building a brand new home

Building a new home takes time and is often carried out at the mercy of the British weather. That is why it is difficult to confirm the exact moving in date until the home is nearly complete. However, the following schedule will give you an idea of what to expect and how your new home is progressing:

Stage 1 - Structural work
Foundations and floor slab
Brickwork up to first floor
Floors in
Complete brickwork, roof and make watertight

Stage 2 - First fix
Initial plumbing
Main plumbing
Main electrical work
Main carpentry, staircases
Internal ceilings, formation of rooms
Drylining (plasterboard lining)

Stage 3 - Second fix
Taps, sanitaryware
Sockets and switches
Architraves, skirting and doors
Wall tiles, if applicable
Decoration

Stage 4 - External works
External works
Rendering finishes
Garden, patio, fencing

Stage 5 - Finals
Customer choice kitchen fitted
Floor tiles, if applicable
Final plumbing, electrical work and carpentry
Final decoration
Final site manager's inspection
Final customer care inspection and cleaning prior to occupation

Your safety is important to us
When visiting a development, your safety is of great importance to us. Building sites can be dangerous places so please follow the guidelines on our signage and ensure any children visiting with you are always supervised and kept away from working areas.

View our developments
Find properties